Lexpert Magazine

April 2016

Lexpert magazine features articles and columns on developments in legal practice management, deals and lawsuits of interest in Canada, the law and business issues of interest to legal professionals and businesses that purchase legal services.

Issue link: https://digital.carswellmedia.com/i/654684

Contents of this Issue

Navigation

Page 41 of 71

42 LEXPERT MAGAZINE | APRIL 2016 faith toward each other. ere is an implied duty not to lie or mislead. "e ruling has caused ripples in many areas of commerce, including in the in- frastructure and construction space," says Martin. "Oen when we have a dispute in an infrastructure project, there's an al- legation of a breach of this duty of implied good faith." Wilson, though, says the case is unlikely to hurt infrastructure disproportionately. "I think when you work with a lot of pub- lic-sector entities, it is part of what they as- sume must govern their dealings. We have always carried a duty of good faith provi- sion in infrastructure contracts, but [lately] there has been some tweaking of the docu- ments. Does the language you've used with respect to the duty of good faith properly bring in the duty as you've draed it?" Another recent SCC decision focuses narrowly on the construction sector. In September 2015, in Stuart Olson Dominion Construction Ltd. v. Structal Heavy Steel, the high court held that a lien bond has no effect on the existence and application of trust remedies under provincial construc- tion lien legislation. "e ruling will affect private projects more than public ones as the lien legislation across the country does not apply to all public projects," says Jane Sidnell, a partner at Rose LLP in Calgary. When an owner or contractor has liened on a construction project, the lien can be discharged by posting either cash or a bond. In the Stuart Olson case, a bond was posted. e issue was whether the contrac- tor who posted the bond still had a trust obligation to the lien claimant. e SCC said the obligation existed, separate and apart from the lien bond. A lien bond, the court ruled, does not extinguish an owner or contractor's trust obligations under the statutory trust and does not amount to a "double payment." "I think we all knew this, but this case brought it into greater clarity," says Sidnell. e case will likely affect how lien bonds are used and trust monies are handled by owners, contractors and sub-contractors (and advice given by construction lawyers). Recent British case law, meanwhile, has boosted recognition in Canada that boil- erplate exclusion clauses will not reduce exposure for consequential (i.e., indirect) damages in construction projects. "Do we have any recent decisions [in Canada] that are astounding? No," says Sidnell. "But is this something on the verge of happening in a very significant way? Absolutely." Infrastructure lawyers have to be careful to cover off the risks of consequential dam- ages, she says, "because relying on those old boilerplate clauses is not going to do the trick." Parties oen cite a contract's blan- ket exclusion of consequential damages, not understanding that in fact that doesn't exclude such eventualities as loss of profit, delay damages, increased production costs, overhead and the cost to remove defective equipment from a site. "You wouldn't want to enter into a con- tract that could take down your company," Sidnell adds. "You may not want to do $50 worth of welding if you're going to be sued for $500 million in the event you acciden- tally blow up the plant." In Québec, the Superior Court has up- held the Québec Ministry of Transport's policy of disqualifying firms that con- tribute to the design or construction of a project from bidding on the contract to supervise the same project. In Roche ltée, groupe-conseil c. Procureur Général du Qué- bec, the court ruled that Roche Consulting Group, having done the plans and designs for a highway, was legitimately excluded from bidding on the supervisory contract. "Now, when a project comes out," says Yvan Houle, a partner at the Montréal of- fice of Borden Ladner Gervais LLP, "the engineering firms have to decide what they're interested in doing, knowing that if they win the design phase, they won't be eligible to do the supervision." Up until 2011, the Ministry's tenders for road works would include bids for both design and supervision. "In hindsight, peo- ple saw that as a conflict of interest," says Houle. "e same engineering firm that prepared the specifications could be super- vising the work carrying them out. If there were deficiencies in the specs, the engineers would point the finger at the contractor, saying it was an execution rather than a de- sign problem." In Ontario, the construction industry is awaiting possible changes to the Construc- tion Lien Act, which has been under review by an expert panel for the past year. Its rec- ommendations, which were to be present- ed at the end of March, could well resonate in other provinces, says Glenn Ackerley, a partner at WeirFoulds LLP in Toronto. He says the expert panel recognizes that there's a strong desire from the trade con- tractors for prompt payment legislation. "But at the same time they're balancing the interests of others in the industry with that. e issue of timely payment will be addressed in some form. Does that mean statutory payment periods? Yes, perhaps, but with exceptions for certain types of projects. For example, statutory prescrip- tion may not apply to home renovations." Currently, the Construction Lien Act requires a 10 per cent hold-back of pay- ments all along the contracts chain. e experts may urge that the release of hold- backs become mandatory on the expiry of | INFRASTRUCTURE | TOBOR EMAKPOR OSLER, HOSKIN & HARCOURT LLP "On an LRT project, you want to bring in your rail specialists and on a power procurement, your power specialists. But the basic contractual documentation typically follows the P3 template. Although the language may be different, the general principles are the same."

Articles in this issue

Links on this page

Archives of this issue

view archives of Lexpert Magazine - April 2016