Lexpert Special Editions

Special Edition on Infrastructure 2016

The Lexpert Special Editions profiles selected Lexpert-ranked lawyers whose focus is in Corporate, Infrastructure, Energy and Litigation law and relevant practices. It also includes feature articles on legal aspects of Canadian business issues.

Issue link: https://digital.carswellmedia.com/i/712992

Contents of this Issue

Navigation

Page 24 of 39

WWW.LEXPERT.CA | 2016 | LEXPERT 25 ment/contract negotiation phase and the actual construction phase." Aer the contracts are nego- tiated and signed, the project team's makeup oen changes. A new team may become responsible for building the project. "What I've seen in the last five to seven years is that the construction team puts the contract in the drawer – typically without reading it – and pro- ceeds to build the project based on their own ex- perience and what they think is best," says Martin. e owners may feel they are paying for some- thing they're not getting because the construction team has gone and done their own thing. "Yet they're reluctant to bring lawyers into the picture," says Martin, "because historically you only have lawyers involved when you have litigation." More sophisticated clients try to avoid this disconnect by making sure there is a transfer of knowledge from the contract negotiating team to the construction team. en that team can man- age the construction as it sees best, but in keeping with what was contractually agreed. In most construction contracts, when contract- ors have a claim for a delay or a cost overrun they must give timely notice, e.g., within seven days of first experiencing the delay. Oen, however, con- tractors fail to give that notice because they're too focused on trying to solve the problem. ey may only belatedly ask the owner for an extension of time and additional payments. Litigation frequently arises over whether a con- tractor's delay claims should be denied because they failed to give timely notice. If, say, the contractor was delayed because the owner's consultant was taking too long to answer the contractor's ques- tions, the owner could have pressed the consultant for a more timely response. Failing to inform the owner until the end of the construction leaves it too late for the owner to resolve the problem. In addition to cost overruns, delays are a huge pitfall for potential litigation. ere has been in- creased public pressure in recent years for infra- structure projects to be completed on time. Also, the funding given to municipalities by provincial or federal governments for infrastructure typically has an end date by which it must be spent. is means that infrastructure contracts oen carry a liquidated damages clause — the contract- or is required to pay the project consortium's lend- er X dollars per day for every day the project is late. e contractor will then try to pass the penalty on to the sub-contractor or designer whom they con- sider responsible for causing the delay. "Two weeks late in the context of a P3 could have hundreds of thousands of dollars of consequences," says Glenn Ackerley, a partner at WeirFoulds LLP in Toronto. Unexpected soil conditions are another major issue that can arise. Unless the ground is fully excavated before the construction phase begins, Madras, Mark L. Gowling WLG (416) 862-4296 mark.madras@gowlingwlg.com Mr. Madras specializes in the practice of environmental law, including environmental issues in project approvals, regulatory compliance, commercial transactions and dispute resolution. MacWilliam, Alexander G. Dentons Canada LLP (403) 268-7090 alex.macwilliam@dentons.com Mr. MacWilliam advises Canadian and international clients on all legal issues relating to the environment. These include regulatory approvals, compliance, contaminated land, climate change, transportation of dangerous goods, dealing with regulatory agencies, responses to government policies and the development of internal environmental practices and systems. MacDonald, Ross A. Stikeman Elliott LLP (604) 631-1367 rmacdonald@stikeman.com Mr. MacDonald's diverse real estate and commercial practice emphasizes acquisitions, leasing, financing and all aspects of major multi-use real estate development projects. His practice also includes working on real estate- based infrastructure projects, such as the Vancouver/Richmond/YVR Canada Line rapid transit project. Macaulay, David J. Bennett Jones LLP (403) 298-3479 macaulayd@bennettjones.com Mr. Macaulay represents domestic and international developers of commercial energy projects, with an emphasis on structuring power, pipeline, oil and gas, storage and other infrastructure projects. Lyons, Catherine A. Goodmans LLP (416) 597-4183 clyons@goodmans.ca Ms. Lyons counsels private and public-sector clients in planning and environmental law and social licence. Her brownfield and greenfield redevelopment experience includes cost-sharing agreements, infrastructure financing and environmental approvals. Lutz, J. Steven Bennett Jones LLP (416) 777-5732 lutzs@bennettjones.com Mr. Lutz specializes in project, asset-based, cross-border, equipment and syndicated financings. His clients include Canadian and international banks, project developers, private equity and borrowers. LEXPERT-RANKED LAWYERS

Articles in this issue

Links on this page

Archives of this issue

view archives of Lexpert Special Editions - Special Edition on Infrastructure 2016